Live build journal · Houston Bay Area

Oleander

An elevated two-unit build followed from the first piling through the final walk.

Follow the build
Now building
ProjectElevated duplex
Current phaseFoundation mobilization
Next field milestonePilings · Sept. 22–23
Journal updatedSeptember 20, 2026

Two residences.
One carefully coordinated build.

Oleander begins on a vacant Gulf Coast lot and rises on a treated timber piling foundation. The building is elevated above grade, with two mirrored residences planned as one structural, architectural, and construction system.

This journal will show the work that finished photographs usually hide: layout, pilings, framing, weather protection, systems, inspections, finishes, and the decisions that connect every stage.

012

Mirrored residences

02≈2,625

Total square feet

0335

Treated 10×10 pilings

04Elevated

Gulf Coast foundation

Front design rendering of the elevated Oleander duplex
Design direction · Front elevation
Floor plan excerpt showing the mirrored Oleander duplex layout
Two mirrored units · One coordinated plan

What happens below the finished floor matters.

The first visible milestone is also one of the most important. The piling grid carries the elevated floor system and establishes the geometry that every stage above it must follow.

We will document the real sequence as it happens—showing how drawings become field layout, structural work, and eventually a completed property.

From pilings
to completion.

Follow each major construction milestone here as the Oleander duplex moves forward.

  1. 01
    Complete

    Design, engineering & approvals

    The mirrored two-unit plan, elevated foundation system, structural details, wind requirements, and permit package were coordinated before construction release.

  2. 02
    In progress

    Site layout & preparation

    The vacant lot is being laid out for the elevated structure, access, utilities, drainage, parking, and the first structural work.

  3. 03
    Next milestone

    Treated timber pilings

    Thirty-five treated 10×10 timber pilings establish the foundation grid for the elevated duplex. Installation is scheduled for September 22–23, subject to weather and field conditions.

  4. 04
    Upcoming

    Stringers, floor system & framing

    The elevated beam and floor system will connect the piling grid before wall and roof framing bring the duplex above the site.

  5. 05
    Upcoming

    Dry-in, systems & exterior

    Roofing, impact-rated openings, weather protection, plumbing, electrical, HVAC, and the exterior envelope move the structure toward a controlled interior.

  6. 06
    Upcoming

    Interiors, closeout & completion

    Finishes, fixtures, final inspections, site work, and closeout turn the construction sequence into two complete residences.

We are showing the build—not just the reveal.

Watch for new Oleander updates as the pilings go in and the elevated structure begins to take shape.